DevelopingIndu Mill Ambedkar memorial faces delay as Rs 350-crore cost proposal awaits state nod
The statue at the Indu Mill Ambedkar memorial in Mumbai has been stalled for six months, as the state government is yet to clear a proposal for an additional Rs 350 crore. The project, originally due this year, is now likely to take two more years.
Costs rose as copper and bronze prices climbed sharply, making it hard for the contractor to continue statue work at the original rates, a rise reportedly linked to tensions in West Asia. The contractor has sought compensation, a proposal reportedly pending for six months. Structural work on the library, auditorium and museum is nearly 95 per cent complete.
The 2018 contract was worth about Rs 763 crore to Rs 783 crore, and the estimate has since risen to around Rs 1,089 crore. With the latest escalation, the total is expected to cross Rs 1,200 crore.
Anand Raj Ambedkar, grand-nephew of Dr Ambedkar, alleged the government was deliberately delaying the project. Harshwardhan Sapkal, Congress state president, said the government did not want to complete it. Bawankule said money would be arranged and the project completed as soon as possible.
Key points
- Work on the Indu Mill statue in Mumbai has been at a standstill for half a year.
- A request for another Rs 350 crore is still waiting for the state government's decision.
- Costlier copper and bronze have made the original rates unworkable, and the contractor wants compensation.
- Buildings housing the library, auditorium and museum are close to 95 per cent finished.
- Completion, originally due this year, is now likely to slip by two more years.