The Brihanmumbai Municipal Corporation is accelerating two projects at Bhandup, a new 2,000 million litres per day (MLD) water treatment plant and a matching pumping station. The BMC says rising population and steady growth in water demand make the projects important for the city's long-term water security. Additional Municipal Commissioner (Projects) Abhijit Bangar has asked officials to finish all works ahead of schedule through close coordination between departments.
During site inspections, Bangar reviewed civil, electrical, mechanical and water treatment work and directed agencies to deploy more manpower and machinery. Excavation for the treatment plant has reached 16 metres across about six hectares, and the remainder is to be completed by May 31, 2027. The plant will use Actiflo technology, dual media filters and other systems.
At the pumping station, 18 of the planned 20.5 metres of excavation are complete, and excavation for the bypass line, rising main and pump house is fully done. The inlet chamber and clear water pumping sump are about 85 per cent complete, and all 179 micropiles have been concreted. Bangar asked for clear timelines for every construction stage.
Key points
- The BMC is accelerating a 2,000 MLD water treatment plant and matching pumping station at Bhandup.
- Additional Municipal Commissioner Abhijit Bangar has directed officials to finish the works ahead of schedule.
- Treatment plant excavation has reached 16 metres, with the remainder due by May 31, 2027.
- Pumping station excavation is 18 of the planned 20.5 metres complete.
- All 179 micropiles at the pumping station have been concreted.