The Supreme Court has held that in incomplete housing projects, where banks released large loan instalments to insolvent or rogue builders, commercial courts, the NCLT or the NCLAT cannot ask flat buyers to repay the financier without first examining the alleged bank-builder nexus. A bench of CJI Surya Kant and Justices Joymalya Bagchi and V Mohana gave the ruling on a petition by Krishna project homebuyers in Gurgaon, whose builder Raheja Developers is in insolvency. The petitioners said the bank had begun recovery proceedings in a Saket commercial court in Delhi although they had not received their flats.

The bench said the commercial court must determine whether the bank disbursed loans strictly under the tripartite agreement, and barred coercive action against the petitioners until that is decided. It said no interim payment direction could be issued unless homebuyers were found to be in default.

In a separate Bengaluru case involving over 4,000 homebuyers, the court granted protection from bank recovery as the project had stayed incomplete for nearly a decade. The bench asked the petitioner's counsel to approach the Karnataka High Court for relief.

Key points

  • The Supreme Court ruled that courts must examine any bank-builder nexus before ordering homebuyers in incomplete projects to repay loans.
  • The ruling arose from a petition by Krishna project homebuyers in Gurgaon, whose builder Raheja Developers is in insolvency.
  • The bench barred coercive action against the petitioners until the court determines whether they are in default.
  • In a Bengaluru case involving over 4,000 buyers, the court granted protection and referred the petitioner to the Karnataka High Court.