Speed restriction of 75 kmph lifted on Igatpuri–Manmad rail route near Nashik
Central Railway said it had completed track improvement work on the Igatpuri–Manmad route, where technical defects near the Banganga Bridge at Kasbe Sukene yard had led to a 75 kmph speed restriction. The restriction had been in force for more than two years and has now been removed, so trains can run at the section's designated maximum speed of 130 kmph. The Bhusawal Division completed the work on November 16.
According to the railway, engineers reworked the track alignment. An unnecessary curve of about 43 metres was straightened, point 101B was shifted by around 330 mm towards the down line, and crossover 102A/B was removed. The main track was then moved about 350 mm towards the down line using mechanical jacks, creating a continuous and straighter alignment from the bridge to the adjoining section.
The railway said the work is expected to improve train speeds, operational efficiency and punctuality on the corridor. The development comes ahead of the Nashik-Trimbakeshwar Simhastha Kumbh Mela, when lakhs of devotees are expected to travel to Nashik and Trimbakeshwar. Removing the restriction will also help railway authorities plan additional special trains and manage the expected rise in passengers.
Key points
- Central Railway lifted a 75 kmph speed restriction on the Igatpuri–Manmad route that had lasted more than two years.
- Trains on the section can now run at the designated maximum speed of 130 kmph.
- The Bhusawal Division completed the track work near Banganga Bridge on November 16.
- Engineers straightened a curve, shifted a point and the main track, and removed a crossover.
- The work is aimed at handling the expected crowds for the Nashik-Trimbakeshwar Simhastha Kumbh Mela.