DevelopingUttar Pradesh cabinet approves Data Centre Policy 2026 aimed at over 2 GW capacity
The Uttar Pradesh cabinet approved the Data Centre Policy 2026 on 6 July 2026, and it replaces the 2021 policy. Policy documents on the Invest UP portal say the aim is to add more than 2 GW of data centre capacity in the state and to attract over Rs 2 lakh crore in investment.
Investors would get an interest subsidy of up to Rs 50 crore for data centre parks and a capital subsidy of up to Rs 20 crore for individual data centre units. Land subsidy ranges from 25 per cent in Madhyanchal and Paschimanchal to 50 per cent in Bundelkhand and Purvanchal. Land bought or leased from government authorities attracts a 100 per cent stamp duty waiver, and power duty is waived 100 per cent for 10 years.
Under the 2021 policy the target was 250 MW and Rs 20,000 crore in investment. State figures up to June 2025 showed 644 MW of proposed capacity and 101 MW operational. In January 2026, the state signed an MoU with AM Green for a 1 GW data centre in Greater Noida, worth 25 billion dollars; an MoU expresses intent, and the project has not been built yet.
Key points
- The Uttar Pradesh cabinet approved the Data Centre Policy 2026 on 6 July 2026, replacing the 2021 policy.
- The policy aims to add over 2 GW of data centre capacity and attract more than Rs 2 lakh crore in investment.
- Investors would get interest and capital subsidies, land subsidies, and stamp duty and power duty relief.
- State figures showed 101 MW operational by June 2025, against a 2021 policy target of 250 MW.
- The January 2026 MoU with AM Green for a 1 GW project in Greater Noida expresses intent, and the project has not been built yet.